2/23/21. The wall construction at the HOA Par 3 is completed. There are 5 houses that are on a minor punch list task completion, receiving grout between the party wall and HOA Par 3 colunm. This task is scheduled to be completed by Thursday 2/25/21. Exterior grading has been completed as well as of 2/22/21. All other construction tasks are finished. Excited to deliver the completed area back to the community. Thank you all for your patience and great cooperation during construction!